Greenfield vs Brownfield Investment in Vietnam

Separate the value of an existing operation from the work required to make it yours.

A ready-built factory in Vietnam can save construction work without saving the work of establishing a compliant business. Greenfield investment creates a new operation; brownfield investment reuses an existing facility or business. Prefer greenfield when your required process and controls need a fresh design. Prefer brownfield when valuable capacity, rights or customer relationships can be demonstrated to remain usable after the deal. The decisive question is what you can actually operate, and what must still be rebuilt.

Key takeaways

  • Evidence of usable capacity matters more than the age of a building: inspect the equipment, site rights and permitted activity together.
  • An equity purchase preserves the target company and its history; selecting assets changes the transfer and consent work instead of making all risk disappear.
  • A new Vietnamese company can use an existing factory, so the physical investment choice and the company acquisition choice are separate decisions.
  • Give brownfield credit only for verified continuity; exclude unsupported revenue, licence or timetable assumptions from the investment case.
  • Prepare a route comparison at the same operating milestone, including remediation, integration and working cash, before committing funds.

Identify the investment perimeter

Start by naming the transaction object: a company, selected assets, an investment project, or access to a facility. Those objects carry different evidence and approval requirements. “Greenfield” and “brownfield” describe commercial investment patterns; they are not separate Vietnamese company forms or a choice between foreign and Vietnamese ownership.

In its discussion of entry modes, the Government of Canada describes brownfield investment as buying or leasing existing facilities, including through mergers and acquisitions. The OECD’s FDI classification separately distinguishes new investment, capacity expansion and acquisitions. These descriptions help frame a project, but neither establishes the Vietnamese legal route for your transaction.

Investment perimeter What you seek What remains to establish
New operation and new facilities Design, technology and controls tailored to the business Site suitability, project pathway, construction or fit-out, recruitment and customer ramp-up
New company using an existing facility A usable building or production footprint without buying the operator Lease or asset rights, adaptation, own permissions and operating systems
Purchase of the operating company’s equity Continuity of the legal entity and its commercial platform Ownership eligibility, historical exposure, control rights and required change approvals
Purchase of assets or an investment project Specified capacity or a defined project without buying every share Exactly which rights, obligations and approvals move, remain or require replacement

The hybrid option is especially useful when the factory is suitable but the operating company is not. Conversely, buying a company may be worthwhile where customer approvals, a technical team and established processes are difficult to recreate. A new company does not necessarily mean a new factory. Keep the physical perimeter and the legal perimeter in separate columns of the investment paper.

Define the asset you need

Identify whether the investment depends on a site, a production line, a customer platform or the operating company before comparing entry routes.

Test what survives the transaction

Use a continuity ledger to remove advantages that exist only in a seller presentation. For each item, record the evidence inspected, its owner, the action needed at closing and the consequence if it fails. The ledger below is a planning tool, not a statement that every listed consent is legally required.

Claimed brownfield advantage Evidence to inspect How to treat an unresolved gap
Ready-to-use premises Land and lease documents, permitted use, remaining term, access and relevant consent clauses Cost a replacement site or make verified access a condition
Production capacity Independent inspection, maintenance history, utilities, usable output and product specifications Use tested output; budget refurbishment and commissioning
Operating permissions Licence holder, covered activity and site, validity, change triggers and outstanding compliance notices Remove assumed continuity until the applicable route is confirmed
Existing customers Signed contracts, termination or control-change clauses, collections and concentration of sales Stress-test retained demand and obtain critical confirmations
Established workforce Employee records, key-person dependence, accrued obligations and retention needs Price retention and transition work; identify replacement capability
Clean financial history Reconciled accounts, tax records, debt, guarantees, disputes and related-party balances Investigate exposure; allocate protection rather than assume it vanishes

For a share purchase, the target remains the contracting entity, but that does not establish that every licence, finance agreement or customer arrangement is unaffected by a change of ownership. For an asset purchase, do not assume that the seller’s contracts or permits accompany the equipment. Check the underlying instrument and applicable rule for each critical item.

Mark each row “verified”, “fixable before operation” or “unresolved”. These are diligence conclusions, not official approval statuses. Give immediate operating value only to the first category. Assign a named action, cost allowance and dependency to the second. Where the investment thesis depends on the third, postpone the decision or compare a replacement plan. Unverified continuity is not a saving.

A route comparison becomes clearer when the same operating requirement is followed through both alternatives. The brownfield branch earns a time advantage only after reuse is established; the greenfield branch earns design freedom only if the startup plan can deliver it.

Compare building capacity with verified reuse A required Vietnam operation separates into building new capacity and reusing existing capacity. Validate the startup plan or verify continuity, then cost missing work and compare operational readiness before choosing. Required Vietnam operation Greenfield Build new capacity Brownfield Reuse existing capacity Validate site and startup plan Verify rights and liabilities Cost the missing work Compare cash and delay to readiness Choose on verified operating value
Existing capacity has value only to the extent it can support the proposed operation after the transaction.

Check Vietnam’s approval gates

Foreign investors should screen access before negotiating an unconditional commitment. Article 8 of the 2025 Law on Investment makes market access dependent on the activity and relevant conditions, including permitted ownership and investment form. Reusing a Vietnamese business does not override those conditions. Align the proposed products, services and ownership chain with the market-access tests for the intended investment before treating either route as available.

New company and new project

Article 19 permits a foreign investor to establish an economic entity before the investment-certificate procedure, subject to market access. Decree 296/2026 , effective July 23, 2026, implements the company-first enterprise dossier exception, including the market-access commitment. This changes sequencing; it does not remove project approvals. Articles 26 and 29 still require an Investment Registration Certificate (IRC) before implementation for covered projects, and investment policy approval where applicable.

An Enterprise Registration Certificate (ERC) establishes the registered enterprise; an IRC records the investment project. For a new entity using an existing building, company formation requirements in Vietnam therefore remain relevant even though construction is reduced. Confirm the project, site and permitted operating scope separately from the company’s incorporation.

Equity acquisition and project transfer

Article 21 requires acquisition registration before member or shareholder changes in specified cases: increased foreign ownership in conditional-access activities; crossing from 50% or below to above 50%, or increasing an already above-50% holding in the specified ownership cases; and specified sensitive-land holdings. Article 26 excludes the equity investment itself from IRC issuance, which does not settle the target’s separate project obligations.

For an investment-project transfer, Articles 33–34 require the relevant transfer conditions and, for covered projects, project-adjustment procedures. Land, housing or real-estate conditions and existing project approvals can affect the result. An asset sale agreement cannot substitute for a required project transfer. Map the chosen transaction against these provisions before fixing its closing conditions.

A separate competition check

Merger control is another screen, distinct from foreign-investment registration. The Ministry of Industry and Trade confirms changes to notification thresholds from July 1, 2026 for the general regime, with financial-sector exceptions. The temporary resolution’s effective period runs through February 28, 2027, subject to the applicable transition and subsequent rules. Assess the proposed concentration and relevant group figures before closing; a modest target price alone does not establish that no filing is needed.

Untangle the approval dependencies

Check whether company formation, acquisition registration, project adjustment or merger control changes the intended implementation plan.

Compare cash and delay to readiness

Compare the routes at the same milestone: an operation able to deliver the required product or service with the necessary rights, people and systems. A company registration date and an acquisition signing date are not comparable endpoints. Neither proves operational readiness.

For greenfield, the cash model should include site access, fit-out or construction, equipment, professional and official charges, recruitment, commissioning and cash consumed before customer receipts. For brownfield, separate seller consideration from cash that actually reaches the operating business. Add due diligence, transaction work, refurbishment, compliance remediation, retention, systems integration and working-capital replenishment. Record VAT and transaction-tax treatment separately after deal-specific tax review; do not assume one blanket rate.

Keep purchase consideration and operating cash separate. Paying the seller for shares does not itself fund payroll, inventory or repairs. Equally, charter capital is company funding rather than a government fee. Avoid counting the same cash twice when reconciling equity, debt, available cash and planned capital injections.

Build a dependency schedule rather than assigning a generic number of weeks to each route. For brownfield, identify the latest of required approvals, critical consents, equipment acceptance and remediation completion. For greenfield, identify the dependencies around site readiness, project approvals, commissioning and customer qualification. These are planning milestones, not statutory processing periods.

Run a downside case by removing one supposedly inherited advantage, such as a key contract or a usable production line. Then recalculate cash needed before receipts and the operating start date. If the brownfield case only works when every optimistic assumption survives, its apparent speed or price advantage is fragile. Request scope-specific estimates instead of applying a universal Vietnam acquisition or setup price.

Turn findings into conditions and handover

Translate the ledger into a short responsibility schedule before negotiating the final documents. Every material gap needs a responsible party, evidence of completion, a deadline and a consequence if unresolved. Legal, tax, technical and environmental specialists should examine their respective risks; one commercial checklist cannot establish all of them.

  1. Freeze the perimeter. List the equity, assets, contracts, project rights and excluded items precisely, with records that identify the legal owner.
  2. Separate signing from implementation. Identify required registrations, approvals and critical consents; structure the agreement so parties do not implement the deal prematurely.
  3. Allocate discovered exposure. Consider seller remediation, a price adjustment, retention or indemnity where legally appropriate; assess whether the protection is collectible and enforceable.
  4. Specify the operating handover. Agree access to premises, equipment acceptance, records, systems, key people and customer communications, including authorised control of company accounts.
  5. Verify the closing file. Reconcile executed transaction documents, applicable official outputs, updated company or project records, payment evidence and the agreed completion checklist.

For greenfield, use the same discipline with landlords, equipment vendors and contractors. Define acceptance tests and the documents needed to use the site and equipment as intended. This prevents a fresh start from becoming an open-ended construction or commissioning commitment.

For brownfield, a certificate folder is only part of the handover. Check that the operating team can access records and systems, understand outstanding obligations and manage the transition. Preserve supporting diligence records and assign owners for post-closing actions. Where an approval or critical right is missing, change the implementation plan rather than merely recording a promise to obtain it later.

Choose usable capacity over a route label

Choose greenfield when the scarce resource is a process, layout or control system that the available targets cannot supply economically. Choose brownfield when the scarce resource is proven usable capacity, a defensible commercial platform or an effective team that would take significant effort to recreate. Consider a new company in an existing facility when reuse is valuable but acquiring the operator is not.

Make the first investment decision conditional on evidence: a defined perimeter, an available foreign-investor route, a completed continuity ledger and a funded readiness plan. Stop if the business case relies on a licence, land right or revenue stream whose continued use cannot be established. The best route is the one that delivers the required Vietnam operation with risks you can identify, price and manage.

Prepare the route decision

Use the proposed activity, ownership chain, target or site documents and readiness assumptions to define the next verification work.

Frequently asked questions

Does brownfield mean contaminated land?

Not necessarily. Investment discussions often use the term for reuse of an existing facility or business. Environmental condition is a separate diligence question; commission an appropriate site assessment where the activity and history warrant it.

Can a minority stake deliver a brownfield strategy?

It can provide an interest in an existing business, but assess whether the agreed governance and commercial arrangements deliver the access or influence your strategy needs. The investment label does not establish operational control.

Should a seller’s historic revenue determine the purchase price?

Treat it as evidence to test. Reconcile revenue with collections, recurring demand, customer dependence and the operating perimeter being acquired. Revenue that depends on an excluded asset or departing team member may not support the buyer’s case.

Is a seller warranty enough to close a continuity gap?

A warranty may allocate risk between parties, but it does not issue an approval, release security or bind a customer to remain. Decide whether the issue needs completion before implementation, a workable fallback or enforceable financial protection.

What should the first investment brief contain?

Describe the investor chain, proposed activity, required output, site or target, transaction perimeter, funding assumptions and the decision deadline. Attach the documents supporting the advantages that matter most so verification starts with the investment thesis.